People, machines and capacity
Create the people and machines your blocks draw on, state what each can give, and see the planned load beside it.
- 4 min read
The Resources page
Open Resources in the left pane. It is one table for the whole workspace, with a row per resource and the columns Resource, Type, Capacity, Demand, Excess and State. Capacity is what you state; Demand and Excess are added up from every canvas that assigns the resource. Click a row to open its inspector on the right.
Illustration to come
Add a person or a machine
- Choose Add resource. A new row appears with its name ready to type.
- Set the Type: person, cohort (several people counted together, with a head count), machine, agent, supplier (billed per hour, order, unit, request or month) or other.
- Use the person’s name or their role; both work. Blocks pick resources from this list on their Resources tab.
A rate for cost can be stated on the resource too; it is used only once you calculate, and only for the cost figures.
State the capacity
Capacity edits inline: click the Capacity cell and enter an amount, a unit and a period, such as 35 hours per week for a person or 40 hours per week for an oven. You choose the units; nothing is assumed. The inspector shows the same figure as Stated capacity.
Leave it empty if you do not know yet. The comparison for that resource then reads Comparison unknown rather than a number.
Read demand and excess
Demand is the sum of what blocks ask of the resource, from the amounts on their assignments, over the same period. Excess is demand beyond the stated capacity. The State column says which case you are in: Within capacity, Excess unresolved, Excess absorbed, or Comparison unknown. On a canvas, a card whose assigned people are over shows “n above capacity” as a small signal.
Excess is a figure to look at, not a verdict on anyone. It can come from the volume of work, from the capacity figure, or from the estimates on the blocks, and often from several at once. The capacity lesson walks through one example.
Stating capacity honestly
A forty-hour week is rarely forty hours for mapped work. Some of it goes to things nobody draws (questions, small favours, finding a file), some is set aside on purpose (training, maintenance), and some is displaced by events that are likely but not scheduled. The inspector shows Reserved draws when a resource has them, but there is no way to enter them on this page yet. Until there is, state the capacity you consider genuinely available for the work on your maps, and say in the resource’s name or in a Note what you have left out.